TM 5-3895-374-10
Item
Procedure
4
Raise the two rear support legs.
5
Connect the transport vehicle and move the generator trailer as desired.
12.Control Van Tear Down Procedures
(See Figure 2-3)
Item
Procedure
1
Remove the computer monitor, keyboard and printer and store in storage
boxes.
2
Remove the air filter element from the ECU. Store in the MCC room for
transport.
3
Install the transport cover onto the ECU.
4
Remove the stairs and store on the control van trailer goose-neck.
5
Remove the ground wire connected from the control van to the ground
rod. Remove ground rod.
6
Raise the trailer using the landing legs so that the weight is removed from
the screw jacks.
7
Remove the pads from the screw jacks and stow the pads and legs in the
transport position. Install the strap preventing the rear screw jack pads
from turning.
8
The trailer will be supported by the wheels and landing legs.
9
Connect the transport tractor and move the control van as desired.
The M081 Asphalt Mixing Plant is in the transport mode. Prior to movement of the plant or any components a Movement
PMCS must be completed. See section 3-4 of this manual.
2-7. Plant Movement
1.
All components of the Asphalt Mixing Plant are portable and each component (except the tow
dolly) is mounted on its own semi-trailer for easy transport by road. The tow dolly is a tandem axle
transport unit with a fifth wheel plate (50" height) mounted to its frame. This unit has a tow-eye
and hitch for transport. Table 2-1 shows equipment compatibility with government truck tractors
(prime movers).
page 2 - 67