TM 5-3895-374-10
No.
Panel
Value
Operation
NOTE
The outlet temperature is controlled by the hot oil heater
16
C
Corner panel-the outlet temperature should be greater
than the inlet temperature if heater is operating.
NOTE
As the asphalt temperature reaches the desired temperature the inlet and outlet temperatures will
be within a degree or two of each other. The heater will automatically cut-off. (Comer Panel)
17
A
Feeder panel-select DIVERT on the Divert Switch.
18
A
Feeder panel-select FORWARD on the
Asphalt
Meterinq Pump.
19
A
Feeder panel-select MANUAL on the manual auto
selector switch Asphalt Meterinq Pump.
20
A
Feeder panel-adjust speed on the dial indicator to
approximately 50% Manual Speed.
21
Screen
Verify pump is pumping asphalt by checking the
monitor.
22
Screen
This will appear in the second information line from the
top (it reads asphalt).
23
Screen
260 to
The temperature of the asphalt will be displayed in the
300F
last column.
24
Circulate asphalt for a minimum of 10 minutes to warm
up pump and valves.
25
Visual
Verify that the batcher gate is open.
Check
NOTE
The main gate should be closed (visual check).
26
B
Motor control panel-turn Surqe Bin Air compressor and
Baqhouse Air compressor to the ON position.
Page 2-102