TM 5-3895-374-24-2
Installation
6.
Install trough covers in proper sequence. Properly locate inlet openings. Handle covers with reasonable care to
avoid warping or bending. Attach covers securely to trough. Do not overtighten as cover damage may result.
7.
Rotate conveyor by hand to insure no binding occurs.
8.
Install drive at proper location and in accordance with separate instructions or drawing provided. Install all guards.
9.
Check screw rotation for proper direction of material travel after electrical connections have been made, but before
attempting to handle material. Incorrect screw rotation can result in serious damage to the conveyor and to
related conveying and drive equipment. If necessary, reconnect electrical leads to reverse rotation of conveyor
and direction of material flow.
10.
Attach all gates, feed chute, discharge chute, etc. and connect all safety devices and controls. CAREFULLY
TEST TO INSURE PROPER OPERATION.