TM 5-3895-374-10
Item
Procedure
10
Extend the cylinders and lower the support base until the two pins in the columns can be re-
inserted.
11
Lock the pins in place by re-inserting the clip pins.
12
Push the right control lever to extend and lower the two cylinders mounted on the front support
base.
13
Extend the cylinders and lower the support base until the two pins in the columns can be re-
inserted.
14
Lock the pins in place by re-inserting the clip pins.
15
Shut off the electrical switch on the surge bin hydraulic pump.
16
Using the hydraulic power pack and the control valve bank connected to it extend the levelling
jacks to raise the unit approximately 1/4" off the ground.
17
Placing a four foot level on the main beams at the front and rear of the unit and using the
hydraulics, adjust the hydraulic levelling jacks until the unit is level front to back.
18
Secure and lower the rear screw jacks to accept the weight of the unit.
19
Adjust the screw jacks on the rear support base.
20
Adjust the screw jacks on the front support base.
21
Retract the hydraulic levelling jacks to lower the unit so the weight is resting on the base pads.
22
Check the unit to ensure it is level front to back on both sides.
23
Check the unit to ensure it is level side to side on the front support base and on the rear support
base.
24
Check the unit to ensure it is level side to side on the rear cross member.
25
If the unit is not level, repeat the necessary steps to level the unit.
26
DO NOT PROCEED UNTIL THE UNIT IS LEVEL.
27
Shut off the power for the portable hydraulic power pack and disconnect the hoses to the surge
bin.
28
The air brake lines and transport lighting cables have connections in the drive through area.
Disconnect the two gladhands, 12 volt cable and 24 volt cable from their receptacles. Retract the hoses and cables to
their storage location.
page 2-17