TM 5-3895-374-10
NOTE
Damaged electrical power or control cables may prevent operation of the plant.
1 Control Van Set Up Procedures
(See Figures 2-3 and 2-4)
Position the Control Van according to the site layout that has been determined. This trailer is used to position the
generator trailers. Measure from the control van according to Figure 2-1 or 2-2. Keep the Control Van parallel to both
generator trailers.
Item
Procedure
1
Position the control van according to the site layout.
2
Disconnect the control van from the transport tractor.
3
Remove the transport strap from the two rear screw jack pads. Lower all screw jacks.
4
Raise the trailer on the jacks approximately one inch.
5
Using a four foot level, level the trailer along both its width and length.
6
Install the ground rod and connect to the van.
7
Install the access stairs. The stairs are stored on the goose neck of the trailer during
transportation. Unbolt the stairs, use a fork lift to remove and place in position below the door.
8
The computer, monitor, keyboard and printer are stored for transport. Remove them from their
boxes and install them by connecting them to the computer and 110 volt power outlet.
9
Remove the transport cover from the environmental control unit (ECU).
10
Install the air filter element into the ECU.
page 2--8