TM 5-3895-374-24-2
6.
Center the head pulley between the two pillow blocks and lock the bearing lock collars.
7.
Install the belt scraper onto the mounts.
8.
Lift the discharge hood into place and install and tighten all fasteners.
9.
Install the drive key into the head shaft.
10.
The two piece pulley guard should be install with the drive assembly.
11.
Complete the drive assembly following the instructions in 3-9-8.
12.
Install the hydraulic cylinders onto the conveyor. Install the ins at either end of the cylinder and lock them in place.
Attach the hydraulic lines to the cylinders.
13.
Install the belt tensioner to the mount for the operating position.
14.
Install the tail pulley back onto the conveyor. Install the pillow block bearings and the two bolts holding each of
them in place. Confirm that the pulley is square to the conveyor frame and tighten the bolts. Slide the tail pulley
and shaft so that it is centered within the bearings and tighten the bearing lock collars.
15.
Re-install the return idlers and the clips that hold them in place. Tighten the fasteners on the clips.
16.
Re-install the trough rolls into the frames. Place the spring clips over the ends of the shafts.
17.
Install the idler sets back onto the conveyor.
18.
Remove the padlocks from the breakers and turn breakers on.
Conveyor Belt
The conveyor belt is installed onto the conveyor and the two ends are vulcanized together at the factory. Equipment
designed for this particular application is used for this purpose. Unless equipment of this nature is available locally, the
belt will have to be repaired or replaced using a mechanical clip designed to hold the ends of the belt together.
page 3 - 1324