TM 5-3895-374-24-2
16.
Install the new hopper skirting bolts, nuts, skirting and clamps to the hopper but leave the nuts loose.
17.
Lift the belt feeder frame into place under the hopper and bolt the four hopper supports to both the belt feeder
frame and to the hopper.
18.
Adjust the skirting so that it just contacts the belt and tighten the bolts holding the skirting clamps in place.
19.
Install the tail pulley guard.
20.
Complete the installation of any other components that have been removed following procedures in other sections
of 3-9.
21.
Remove padlocks from the breakers and turn breakers on.
3-9-6
Bin Vibrators
Removal, Repair and Replacement. See figure 3-63.
This procedure assumes a complete removal, repair and replacement of the assembly. A partial disassembly, repair and
replacement is possible. Follow the procedure to the point of removing only those components requiring repair or
replacement. The procedure is the same for all four of the belt feeders.
A.
Disassembly
1.
Disconnect and lock out the breaker for the bin vibrator.
2.
Remove the plug for the vibrator and coil the cable. Check the chassis and hopper for any cable clips holding the
cable in place. Loosen these so that the cable can be removed.
3.
The vibrator is held on with four bolts. Remove these and the vibrator.
B.
Inspection
1.
Have the vibrator inspected and tested by a qualified facility. Repair or replace as necessary.