10.
Connect all heat transfer lines that were disconnected. Follow the markings made during disassembly.
11.
Install the mesh guard around the rear deck.
12.
Inspect all components and confirm that all fasteners are tightened and that all line connections are tight.
13.
Open the heat transfer valves that were closed.
14.
Open asphalt valve that was closed.
15.
Remove padlock from the breaker and turn breaker on.
16.
Upon returning the asphalt metering pump to operation, observe all connections for leaks. Monitor the
flange connections for asphalt leaks. The joints may not seal adequately after they have been raised to
operating temperatures.