TM 5-3895-374-24-1
3.
Install the air cylinder and the gate members into the mount on the bin. Install the eight bolts and washers leaving
them loose until the clevis pin has been install to the gate lug. Extend the cylinder shaft and Install the cylinder pin
into the gate lug and lock the cotter pin In place. Tighten the bolts holding the cylinder in place. Test the gate and
cylinder stroke to see that the gate goes to a fully closed position and can open without the cylinder shaft binding.
4.
Connect the air lines to the cylinder taking care to connect the correct air line to the correct port
5.
Install the heating element and thermostat Reconnect the wiring to these components.
6
Install the Insulation and the sheet metal cover to the gate.
7.
Repeat this process for the other gate.
3-4-15 Electrical Panel
An electrical panel containing the start-stop button for the on-board hydraulics is mounted on the surge bin. This panel,
labelled JB-04, also contains other electrical components. See the electrical drawing AA00402 in Section 3-2-6.