TM 5-3895-374-10
12. Miscellaneous Set Up Procedures
(See Figures 2-15, 2-29, 2-30, 2-31 and 2-32)
Item
Procedure
1
Position the calibration tank as per the site layout Figure 2-29. The valve end should be
positioned toward the asphalt tanker.
2
Assemble the upper portion of the tank frame to the lower portion and install the bolts and
tighten. See Figure 2-30.
3
Unbolt the lower frame from the tank and suspend the tank on the chains provided. See
Figure 2-30.
4
Remove the retainer bolts holding the test weights in position. See Figure
2-30.
5
The electrical power cables can be unwrapped from their transport storage positions and
connected to the control van. The cables are to run parallel to each other in straight lines. See Figure 2-31. Lay out the
power cables in the following order: Surge Bin (laid out and connected during surge bin set up)
Baghouse
Dedrummer/Melter
Asphalt Tanker
Drum Mixer
Feed Conveyor
Four Bin Feeder
6
The electrical control cables can be unwrapped from their transport storage positions and
connected to the control van. These cables are to run parallel-to each other in straight lines. See Figure 2-32. Lay out
the control cables in the same order as power cables.
7
Hydraulic power pack. Store this unit on or near the goose neck of the control trailer. It may
be required for re-leveling of any equipment that settles during operation.
8
Install the fines blower hose (stored in the basket on the dedrummer) from the blower on the
baghouse to the drum mixer. See Figure 2-15.
page 2 - 50
