NORMAL BAGHOUSE OPERATION
Section 6 Maintenance

TM-5-3895-374-24-2 M081 Asphalt Mixing Plant Manual
Page Navigation
  29    30    31    32    33  34  35    36    37    38    39  
TM 5-3895-374-24-2 FEBRUARY 1993 BAGHOUSE SHUT DOWN 1. Stop process feed (dryer operation) 2. Shut down fan 3. Go thru  2 cleaning cycles. Collected material  must not  be allowed  to remain on the bag for a prolonged period of time.  Condensation may form and damage the bags and cause premature blinding (plugging). 4. The screw  conveyors  and airlock  should  continue  to operate  for approximately 10 minutes or until all material is discharged. 5. When  shutting  down  for  prolonged  periods  of  time  or  when  transporting  the  baghouse  to  a  new  location,  the inclined screw conveyor must be emptied by removing the door on the bottom and reversing the motor. page 3-694







Western Governors University

Privacy Statement
Press Release
Contact

© Copyright Integrated Publishing, Inc.. All Rights Reserved. Design by Strategico.