Four Bin Feeder Set Up Procedures - TM-5-3895-374-10_77
Figure 2-24 Four Bin Feeder

TM-5-3895-374-10 Paving Machine Bituminous Material: Crawler Mounted Diesel Engine Driven Manual
Page Navigation
  63    64    65    66    67  68  69    70    71    72    73  
TM 5-3895-374-10 Item Procedure 14 Disconnect the hydraulic power pack. 15 Using a crane and slings, support the ramp plate and remove the two bolts holding it in position. 16 Lower the ramp plate until the two bolts can be re-installed. 17 Repeat this process on the remaining three plates. 18 Position the three ladders by removing the two bolts at the bottom of each and lifting the ladders until the bolts can be re-installed. 19 Raise the bin hopper extensions and bolt into the operating position. 20 Remove the two sections of the calibration tank from bins 1 and 2. 21 Install the belt tension wheel assembly. See figure 2-28. Adjust the belt tension as required on the conveyor screw adjustment at the tail pulley. 22 Build ramp with front end loader using site materiel or aggregates. page 2 - 44







Western Governors University

Privacy Statement
Press Release
Contact

© Copyright Integrated Publishing, Inc.. All Rights Reserved. Design by Strategico.