• Home
  • Download PDF
  • Order CD-ROM
  • Order in Print
Standby Generator Set Up Procedures
Figure 2-5.   Generator Trailer

TM-5-3895-374-10 Paving Machine Bituminous Material: Crawler Mounted Diesel Engine Driven Manual
Page Navigation
  31    32    33    34    35  36  37    38    39    40    41  
TM 5-3895-374-10 Item Procedure 6 Remove the two power cables from the 200 kW generator trailer storage position and connect as follows: Connect the first cable (CBL 137) to generator #1 then feed the other end through the port located below the control van near the goose neck.  Connect the cable to the motor control center #1 in the control van. Connect the second cable (CBL 135) to generator #2 then feed the other end through the large port located below the door of the control van.  Connect the cable to the motor control center #2  in the control van. 4.Hydraulic Power Pack Set Up Procedures (See Figures 2-1 and 2-7) Item Procedure 1 Remove the power pack from its storage position on the goose-neck of the control van.  Use a suitable lifting device. 2 Use the hydraulic power pack as required to set up plant trailers.  When connecting power cord match markings on the cable with the plug at either the van or hydraulic power unit. page 2-12







Western Governors University

Privacy Statement
Press Release
Contact

© Copyright Integrated Publishing, Inc.. All Rights Reserved. Design by Strategico.